IBM i Upgrade Dependency Inventory
A deeper upgrade-planning guide for IBM i teams building the dependency inventory that decides whether a Power 10 or Power 11 migration is ready.
Jump to the exact AS400 software question you want answered.
The Upgrade Checklist Is Not The Project
A checklist tells the team what to consider. A dependency inventory assigns the work, names the owner, and exposes the items that can block a real IBM i upgrade or hardware migration.
This is the next intent step for buyers who already know they need to move toward a supported IBM i release. The driver may be hardware refresh, security, or vendor support.
Inventory Platform Dependencies
Start with the platform dependencies that decide whether the upgrade is straightforward or blocked. IBM's upgrade planning guidance points buyers toward compatibility and pre-upgrade tooling because these details matter before the window is approved.
- IBM i release and Technology Refresh level
- PTF groups
- Firmware
- HMC level
- VIOS if present
- Backup method
- Storage and tape
- Printer and output dependencies
- Scheduled jobs
- System values that affect application behavior
Inventory Application And ISV Dependencies
List every application dependency that touches the partition. For each dependency, record the owner and the status that could block the cutover. The point is not a larger spreadsheet. It is reducing surprise.
- Packaged applications
- Custom RPG or COBOL applications
- Java dependencies
- ODBC or JDBC connections
- EDI paths
- Warehouse interfaces
- Report extracts
- APIs
- Document workflows
- Security tools
- Vendor support status
- Version and license key behavior
- Test evidence and rollback expectation
Decide The Test Sequence
Testing should follow business priority, not file names. Start with the workflows that create revenue or operational risk.
Each test should have a pass condition and a named business reviewer. If nobody can say what success looks like, the upgrade is not ready for that workflow.
- Create revenue
- Ship product
- Close finance
- Process EDI
- Run payroll
- Satisfy compliance
Write Rollback Before Cutover
Rollback planning should be written before the cutover window is approved. A rollback plan is not a lack of confidence. It is what makes a technical upgrade acceptable to the business.
- Last safe point
- Backup state
- Save or snapshot method
- Decision deadline
- Communication path
- Who can stop the cutover
Common questions about this Version Upgrade topic.
What belongs in an IBM i upgrade dependency inventory?
Include every item that can block the project.
- IBM i release
- PTF groups
- Firmware
- HMC
- VIOS
- Backup
- ISV software
- Custom applications
- Java
- ODBC
- EDI
- Printers
- Schedulers
- Reports
- APIs
- License keys
- Owners
- Test status
- Rollback requirements
When should rollback planning happen?
Rollback planning should happen before the cutover window is approved. The team should know the last safe point and the deadline for deciding whether to continue or reverse the change.
Sources
All sections, listed like article footnotes.
Software catalog pages tied to this Version Upgrade topic.
IBM i Operating System Upgrade Planning
A software planning and services category for IBM i release upgrades, PTF strategy, compatibility checks, and version migration readiness.
Database Replication, Mirroring, and Migration
An replication and migration program for real-time synchronization between heterogeneous databases and platforms with one-way and two-way support.
IBM i Backup SnapShot Software
An IBM i backup program built around creating identical LPAR copies quickly and backing up data without the same production impact as traditional methods.